Shimon Ben-El

Reading Calgary building permits as leads

What a permit row tells a trade, before anyone else knows the job exists.

The City of Calgary publishes every building permit it issues, every day, on its open data portal. A permit is a project that has been approved and paid for: somebody is about to build, add, or alter, and the address is on the row. For a trade, that is a lead with a date on it. Here is how to read one.

The fields that matter

How each trade reads it

Setting the filters

Start wide: your quadrant, work class New and Addition, no cost floor, the last seven days. Read the list once and you will see your own filter in it: the two permit classes that matter to you and the cost floor under which you would not drive. Then run it every morning with yesterday's date, or once a week with the week's, and the list is only what is new.

What a permit does not tell you

The row carries no applicant name and no contractor name; this alert does not ask the City for them, by design. The permit holder is at the address, or the site is, and the work is yours to win the old way: a visit, a card, a call to the builder whose sign is on the fence. The row gets you there first; it does not knock for you.

A worked example

Take a new six-storey residential building in Southview, issued last week, estimated in the millions. The framer and the concrete crew were chosen months ago. The trades that are not chosen yet are the ones that come after the shell: doors and hardware, suites of locks, mailboxes, signage, the low-voltage work. That is who should be reading this row today.

See eight real permits from the last seven days

If you would rather have the reading done for you, the permits report is on my Toku profile. The alert itself is on the Apify Store: Calgary Building Permits Alert. Fifteen dollars per thousand permits returned, a cent and a half each.